Due to time damage and due to excavation work by various installation carriers, the city of Vienna – Road Administration and Road Construction begins on Tuesday, May 6, 2025, with definitive lane and sidewalk maintenance work in Pfenndgasse and on the crossing plateau Herbststraße/Pfenniggasse in the 16th district. In order to improve the visual conditions and to shorten the crossing of the road, sidewalks are built on the crossing plateau Herbststraße/Pfenndgeldgasse.
Traffic measures
The construction work takes place during the day. The autumn road is expected to be a dead end for three weeks at the confluence with Pfenndgeldgasse – while at the same time canceling the one -way. During the repair work in Pfenndgeldgasse, there is a stopping and parking ban in the respective work area.
- Location of the construction site: 16th, intersection plateau Herbststraße/Pfenninggeldgasse as well as in Pfenninggeldgasse
- Start of construction: May 6, 2025
- Planned construction end: June 13, 2025
Further information is available on wien.gv.at/verkehr/strassen and wien.gv.at/verkehr/baustellen Or also under +43 1 955 59 – Infoline Straße and Transport.
City of Vienna – street management and road construction
Silvia Aigner
Telephone: +43 1 4000-49812, +43 676 8118 49812
E-mail: silvia.aignner@wien.gv.at
Erwin Forster
City of Vienna – street management and road construction
Public relations
Telephone: +43 1 4000-49811
Mobil: +43 676 8118 49811
E-mail: erwin.forster@wien.gv.at
OTS original text press release with the exclusive in terms of content of the sender – www.ots.at | NRK