Due to damage, such as cracks, exertion and lane channels, in Gaisruck, the lane of the state road B 19, which is frequented in the local area with an average traffic volume of around 5,300 vehicles per day, from the southern start of the local area to the church and the road on the state road L 14 from the intersection B 19 / L 14 to the eastern end of the traffic. The channel was renewed in advance and the ÖBB had been renewed the Rigole for the drainage by the ÖBB at the level crossing at the southern end.
In accordance with the damage picture that has occurred, the entire bituminous structure was renewed over a length of around 360 meters on the state road B 19 from the southern start of the town until shortly before the intersection with Scheunenstrasse. As a renovation measure of the remaining 350 meter long section of the state road B 19 and the approximately 220 meter long section of the state road L 14, a new layer of support and cover was applied after the milling work; Finally, the required floor marking was applied.
The now completed work of the lane renewal over a total length of 930 meters was carried out by Strabag AG in a construction period of seven days, during which the section was closed. The costs for the road renewal amount to around 370,000 euros, which are borne to the state of Lower Austria.
More information at the Lower Austria Straßendienst on 0676/81260141, Gerhard Fichtinger, and email Gerhard.fichtinger@noel.gv.at,
Office of the Lower Austrian state government
State Directorate/Public Relations
Mag. Rainer Hirschkorn
Telefon: 02742/9005-12175
E-mail: pressse@noel.gv.at
OTS original text press release with the exclusive in terms of content of the sender – www.ots.at | NLK