mythics.azura.idevice.co.id

3rd district: Roadway and sidewalk renovation work on the Baumgasse/Franzosengraben intersection plateau | City of Vienna

3rd district: Roadway and sidewalk renovation work on the Baumgasse/Franzosengraben intersection plateau | City of Vienna
Vienna (OTS) –

Due to time constraints, the City of Vienna – Road Administration and Road Construction will begin road renovation work on the Baumgasse/Franzosengraben intersection plateau in the 3rd district on Tuesday, October 8, 2024, at 8 p.m.

Traffic measures:

The work mainly takes place at night, between 8 p.m. and 5 a.m. During the work, it is not possible to turn left from Franzengraben into Baumgasse in a direction out of town. The diversion leads via Franzengraben, Erdbergstrasse, Nottendorfer Gasse to Baumgasse.

It is also not possible to turn left from Baumgasse into Franzengraben. In addition, it is not possible to turn right into Baumgasse at Franzengraben during the work. Traffic will be redirected locally.

The work on the Franzengraben in front of house number 16 will take place between 7 a.m. and 5 p.m. with one lane in the direction of the A 23 – Südosttangente remaining clear.
Foot traffic will be maintained.

There are no traffic measures outside of the stated working hours.

  • Location of the construction site: 3., crossing plateau Baumgasse/Franzosengraben
  • Construction start: October 8, 2024
  • Planned end of construction: October 18, 2024

Further information can be found at wien.gv.at/verkehr/strassen and wien.gv.at/verkehr/baustellen or at +43 1 955 59 – Infoline Road and Traffic.

OTS ORIGINAL TEXT PRESS RELEASE UNDER THE EXCLUSIVE RESPONSIBILITY OF THE SENDER FOR CONTENT – WWW.OTS.AT | NRK

pragmatic play

link slot demo

slot demo

slot demo

Exit mobile version